Indemnity Agreements and Bonds
Posted in Articles by on Sat Nov 22, 2014
Beware that some courts may compel arbitration of a surety’s salvage claims against its principal and indemnitors even if the general agreement of indemnity (the “GAI”) does not include an arbitration provision.
That was the case recently in Hanover Ins. Co. v. Atlantis Drywall & Framing, LLC, 2014 WL 4251586 (11th Cir. August 29, 2014), where the Eleventh Circuit Court of Appeals held that the principal and indemnitors could use a subcontract’s arbitration provision to compel the surety’s claims against them. The Court reasoned that because the execution of the GAI and the subcontract were part of the “same transaction,” the surety should be required to arbitrate its claims against the principal and indemnitors. Surprisingly, it did not matter to the Court that the GAI covered other bonded subcontracts that did not contain arbitration provisions because “the parties entered into the [GAI] with the [instant] subcontract and specific payment and performance bonds in mind.” Cases like these illustrate the need to have experienced attorneys that are aware of these dynamic and sometimes unpredictable currents in surety and construction law.
Share This Postcategories
archives
- September 2024
- May 2024
- March 2024
- February 2024
- January 2024
- December 2023
- November 2023
- September 2023
- August 2023
- July 2023
- April 2023
- December 2022
- October 2022
- August 2021
- August 2020
- February 2020
- July 2019
- June 2019
- September 2018
- August 2018
- May 2018
- April 2018
- February 2018
- July 2017
- March 2017
- February 2017
- January 2017
- September 2016
- July 2016
- September 2015
- June 2015
- May 2015
- April 2015
- January 2015
- November 2014